A new driveway is a large slab with a long life ahead of it, so the details matter. This page walks through what a licensed concrete contractor will measure, what the city cares about, and what to look for in a written quote. Tooele Concrete Works is a referral service that connects homeowners with licensed local contractors, and the contractors do the work.
Start at the street
Your driveway has two halves. The apron, where it meets the street, can cross the public right-of-way, and the city controls that strip. The part on your lot you design with the contractor, but the city has a say there too: Tooele City code 4-1-2 requires a written permit from the Building Official before construction, alteration or repair, except where the work is minor in character as defined in the code or as determined by the Building Official (Tooele City code). Whether your driveway counts as minor is the Building Official's call, so ask Community Development. The city's fee schedule charges 2 x permit fees for work done without a permit (Tooele City fees).
Tooele City code 4-11-1 makes it unlawful to build a sidewalk, curb, gutter or related work in the public right-of-way without city-approved grades and lines and a building permit. Code 7-4-8 limits a drive approach on a one- or two-family lot to 30 feet or one-third of the lot frontage, whichever is less. Both are in the Tooele City code. Rules change, so confirm them with Tooele City Community Development at 435.843.2132.
Here is how the width cap works out. On a lot with 75 feet of frontage, one-third is 25 feet, so 25 feet is the limit. On a lot with 120 feet of frontage, one-third is 40 feet, so the 30-foot cap governs. If you are planning a wide three-car approach, ask the contractor to check the cap before drawing anything. The permits page lists the office, the portal and who to call.
If your driveway connects to a state highway instead of a city street, the state has its own say. UDOT requires a conditional access permit whenever a driveway connection is requested along a state highway (UDOT access management).
Thickness, base and steel
A written quote should name each of these. If it does not, ask.
- Thickness. Concrete Network says a minimum of 4 inches is generally sufficient for passenger cars and SUVs, and that heavier trucks or a large RV may call for 5 or 6 inches (thickness guide). Many municipalities also require the apron at the street to be 5 or 6 inches thick, and Community Development can say what Tooele wants at the apron.
- Base. The compacted subbase and base under the slab should be at least 4 inches thick in total (Concrete Network). The contractor strips sod and topsoil first, because organic soil cannot be compacted.
- Reinforcement. Wire mesh generally suits driveways 4 to 5 inches thick and rebar suits 5 inches or more (thickness guide). Fibers cut early shrinkage cracking but are not a structural substitute for steel (Concrete Network).
- Joints. Concrete Network says a 4-inch slab should have control joints 8 to 12 feet apart (Concrete Network). They are planned crack lines. A slab without them cracks anyway, just not where you chose.
Ground in Tooele Valley
A Utah Geological Survey study says expansive soil is a hazard in Tooele Valley, and that a shallow ground-water hazard may be found there too (Special Study 96). It covers the valley, not your lot. Ask the contractor what they see in the cut: soft spots, wet clay, fill. Settling and heaving can start with what was under the slab.
The mix to ask for
Concrete Network advises a driveway mix of at least 4,000 psi with a water-cement ratio below 0.50 (mix guide). For the street end, the city's own spec for approaches and sidewalks is 4000 psi with 5% to 7% entrained air (code 4-8-2.8, same city code link). Air gives freezing water room to expand, and the American Concrete Institute says it raises freeze-thaw resistance and cuts scaling from ice-removal chemicals (ACI).
A good crew does not add water at the truck to make the concrete easier to work. It weakens the mix.
Pour day and the wait afterward
Cold-weather practices should begin when air temperatures will fall below 40 degrees F in the first 24 hours after placement (Concrete Network). The American Concrete Institute says fresh concrete should be protected from even one freeze until it reaches 500 psi, and from repeated freezing and thawing while saturated until it reaches 3,500 psi (ACI). Ask what happens if a frost is forecast for your pour day. In summer, ideal placement is below 80 degrees F (Concrete Network), so ask what time the pour will start on a hot day.
Then the waiting:
- Walking: at least 24 hours (Concrete Network).
- Cars: typically seven days after placement (Concrete Network).
- RVs and large trucks: at least 28 days (same page).
Keep wheels off the edges early. That can crack a new slab.
Your first winter
Skip deicers the first winter after a driveway goes in, because new concrete is more susceptible to salt damage. Products with ammonium nitrates or ammonium sulfates are especially harmful because they attack concrete chemically (Concrete Network). Sand gives traction without the damage. The same page says to reseal a driveway about every two years, or when the finish shows wear.
Common questions
Will a new driveway crack?
Some cracking is normal on every project, according to the American Concrete Institute (ACI). Cracks wider than a credit card that run through the slab are a different story and call for repair or replacement (Concrete Network).
Who calls 811?
Blue Stakes of Utah 811 wants at least 3 business days' notice before any excavation (Blue Stakes). Ask the contractor who places the call. Point out any private lines you know of, such as sprinkler pipes.
How much will it cost?
Thumbtack's national range is about $8 to $18 per square foot (Thumbtack). A real quote depends on your lot, the tear-out and the finish; see the cost page for the sources and what moves a Tooele quote.
Check a contractor's license on Utah's Licensee Lookup before you hire.
Where these numbers come from: Thumbtack for the national per-square-foot range, the American Concrete Institute and Concrete Network for mix and curing, and Tooele City's code for the street-end rules, all read in November 2026.